==Administrative Paperwork Timeline== | ==Administrative Paperwork Timeline== | ||
− | *3/ | + | *3/03: LOI goes to subs (Sanjay/Rachana) |
− | *3/ | + | *3/31: Signed Subcontractor's Documents due back to BWH |
*4/05: Review by Radiology Administration (Trey/Susan) | *4/05: Review by Radiology Administration (Trey/Susan) | ||
*4/14: Review by BWH RA | *4/14: Review by BWH RA | ||
Line 21: | Line 21: | ||
*4/23: final pdf created and submitted to Rachana (Katie) | *4/23: final pdf created and submitted to Rachana (Katie) | ||
− | =Report | + | ==Scientific Progress Report== |
− | + | *[[media:NA-MIC_APR_no_budget_04.29.11.pdf | 2011 Scientific Progress Report]] | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | * | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Latest revision as of 21:45, 27 May 2011
Home < 2011 Progress ReportBack to NAMIC_Annual_Reports
Administrative Paperwork Timeline
- 3/03: LOI goes to subs (Sanjay/Rachana)
- 3/31: Signed Subcontractor's Documents due back to BWH
- 4/05: Review by Radiology Administration (Trey/Susan)
- 4/14: Review by BWH RA
- 4/28: Signed Docs due back to Katie M for page numbering (Katie)
- 4/29: Ship it to NIH
Scientific Report Timeline
- 3/1: wiki page setup for progress report
- 4/16: all sections to be completed by owners
- 4/16: check NIH compliance of all publications in Pubmed (Katie)
- 4/20: create final report (Ann)
- 4/20: create full publications list (Katie)
- 4/16: final review (Tina, Ron)
- 4/23: final pdf created and submitted to Rachana (Katie)