* 8 Channel Head Coil was used to reduce the impact of EPI spatial distortions, and ASSET (Array Spatial Sensitivity Encoding Techniques, GE) with a SENSE-factor (speed-up) of 2 was used.
 
* 8 Channel Head Coil was used to reduce the impact of EPI spatial distortions, and ASSET (Array Spatial Sensitivity Encoding Techniques, GE) with a SENSE-factor (speed-up) of 2 was used.
 
* Acquisition parameters were as follows: 51 directions with b=700, 8 baseline scans with b=0, TR 17000 ms, TE 78 ms, FOV 24 cm, 144 x 144 encoding steps, 1.7 mm slice thickness. The total scan time for the sequence was 17 minutes.
 
* Acquisition parameters were as follows: 51 directions with b=700, 8 baseline scans with b=0, TR 17000 ms, TE 78 ms, FOV 24 cm, 144 x 144 encoding steps, 1.7 mm slice thickness. The total scan time for the sequence was 17 minutes.
 +
 +
 +
Return to [[Projects/Diffusion/2007_Project_Week_Contrasting_Tractography_Measures | ContrastingTractography Project]]

Revision as of 01:49, 12 July 2007

Home < Projects < Diffusion < 2007 Project Week Contrasting Tractography Measures < Acquisition Parameters

DTI data:

  • 3 Tesla GE system was used to acquire data (General Electric Medical Systems, Milwaukee, WI)
  • We used Echo Planar Imaging (EPI) DTI Tensor acquisiton with double echo option enabled, in order to reduce eddy-current related distortions.
  • 8 Channel Head Coil was used to reduce the impact of EPI spatial distortions, and ASSET (Array Spatial Sensitivity Encoding Techniques, GE) with a SENSE-factor (speed-up) of 2 was used.
  • Acquisition parameters were as follows: 51 directions with b=700, 8 baseline scans with b=0, TR 17000 ms, TE 78 ms, FOV 24 cm, 144 x 144 encoding steps, 1.7 mm slice thickness. The total scan time for the sequence was 17 minutes.


Return to ContrastingTractography Project