Difference between revisions of "2011 Progress Report"
From NAMIC Wiki
Line 20: | Line 20: | ||
*4/16: final review (Tina, Ron) | *4/16: final review (Tina, Ron) | ||
*4/23: final pdf created and submitted to Rachana (Katie) | *4/23: final pdf created and submitted to Rachana (Katie) | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Revision as of 16:14, 5 April 2011
Home < 2011 Progress ReportBack to NAMIC_Annual_Reports
Administrative Paperwork Timeline
- 3/03: LOI goes to subs (Sanjay/Rachana)
- 3/31: Signed Subcontractor's Documents due back to BWH
- 4/05: Review by Radiology Administration (Trey/Susan)
- 4/14: Review by BWH RA
- 4/28: Signed Docs due back to Katie M for page numbering (Katie)
- 4/29: Ship it to NIH
Scientific Report Timeline
- 3/1: wiki page setup for progress report
- 4/16: all sections to be completed by owners
- 4/16: check NIH compliance of all publications in Pubmed (Katie)
- 4/20: create final report (Ann)
- 4/20: create full publications list (Katie)
- 4/16: final review (Tina, Ron)
- 4/23: final pdf created and submitted to Rachana (Katie)