Slicer 3 Dartboard
Link to the Slicer 3 Dartboard here
2008-01-24
Attendees: Jim, Steve, Wendy, Xiaodong, Nicole, Katie, Alex, Luis, Ron, Will
- Project week follow-up (Next week?)
- Loadable modules
- GenerateCLP - Thanks Hans
- AHM Jan 2009, Early January 2009
- Summer Project Week, Jun 23-27, 2008
2008-01-17
Attendees: Jim, Katie, Sebastien, Stephen, Luis, Steve, Wendy, Will
- Luis and Bill Hoffman are making progress in making ITK installation relocatable. This is needed to finish the work on building plugins from an installation.
- What's in VTK 5.2?
- Infovis - Tables, Graphs, Views, IO
- Refinements to WWidgets. Client/Server connections within the widgets. Event translation. New widgets (text, caption, affine, checkerboard, rectilinear wipe, annotation, key frame, contour, measurement, point/placer, plot)
- Build now? Or wait until 5.2 released?
- Repository freeze in March
- Release on April 1, 2008
- ITK release
- Patches to ITK 3.4
- Nine component/six component tensor conversion in IO has been patched to ITK 3.4
- 1/19-2/1 moving contributions on Insight Journal for ITK 3.6
- Move items from Review directory to main tree (QuadMesh, TransformIO) for ITK 3.6
- Freeze repository 2/29 for ITK 3.6
- Slicer3 will need to build against the Review directory.
- Patches to ITK 3.4
- CMake release
- Version 2.6 on the horizon - release candidate in 3 weeks.
- Tcl/Tk 8.5
- Sebastien has a Windows build
- Steve will try it out
- Wait to switch to 8.5 until we have a good reason
- Loadable modules
- Sebastien - working on CMake issues on building modules as loadable modules
- Terry - working on loading modules and reworking Slicer3.cxx
- Event Broker
- DWI DICOM as part of the Load Volume. Xiaodong is working on it.
- ITKFactories directory in build and installs to hold ImageIO plugin libraries. Should increase the speed of executable plugins on the Mac.
- OpenIGTLink
- Protocol on the wiki (message format)
- Put code in Sandbox, SourceForge, NITRC, Google Code???
- Will schedule a time to go over the Project Week results
2008-01-10
No tcon due to AHM
2008-01-03
- Attendees: Jim, Steve, Will, Brad Davis
- Topics:
- Jim and Will talked about leading the Monday and Friday sessions, and who would do what.
- We are going to send out reminders to the project leads to ensure that their project descriptions are up to date
- We discussed the software process project to make sure that we have a chance to address the Slicer build process, dashboards, etc.
- We decided not to hold the project wrap-up presentation at AHM; we will do that later at subsequent TCons. (We decided that we needed the time to actually work. We are concerned that we are starting to see too many break-outs and not enough time to work.)
- We keenly missed Tina and hope that she and her family are doing well.