The project is finished. I am documenting the results in my diploma thesis at the moment.
Steps to go
Slicer | |
---|---|
DONE | Implement slicer module to start Synchrograb from within Slicer |
Create 3D volume with Synchrograb | |
Create ultrasound calibration matrix | |
DONE | Create 3D volume with data from the ultrasound device and the tracker |
DONE | Include options for turning on and off US/Tracker device in cmake |
DONE | Create 3D volume with mockup images and tracking information from the tracker |
DONE | Create 3D volume with mockup images and mockup tracking information |
Synchrograb | |
DONE | Send 3D volume data via OpenIGTLink to Slicer and display data in Slicer |
DONE | Compile Synchrograb core i.d. uncomment unnecessary parts (Ultrasound, Tracker) |
Preparation | |
DONE | Display 3D volume data received via OpenIGTLink with the volume rendering module |
DONE | Create stand alone software to send volume data to Slicer via OpenIGTLink |
DONE | Compile and run Slicer with OpenIGTLink and volume rendering |
Progress - i.e. what I have done so far
Month | Week # | Start Date - End Date | Done | Date Done |
---|---|---|---|---|
February | Week 05 | 27.01 - 01.02 | ||
Slices and tracker matrices are sended to Slicer in real-time | x | Fri Jan, 16th | ||
Week 04 | 19.01 - 26.01 | |||
Literature research complete | x | Thu Jan, 22th | ||
Week 03 | 12.01 - 18.01 | |||
- | ||||
Week 02 | 05.01 - 11.01 | |||
- | ||||
January | Week 01 | 29.12 - 04.01 | ||
- | ||||
Week 52 | 22.12 - 28.12 | |||
Trilinear Interpolation works | x | Wed Dec, 17th | ||
Reconstructed Volume has correct depth | x | Tue Dec, 16th | ||
Week 51 | 15.12 - 21.12 | |||
Created Slicer Module to start Synchrograb within Slicer | x | Wed Dec, 10th | ||
Ultrasound device module works | x | Tue Dec, 9th | ||
Week 50 | 08.12 - 14.12 | |||
Fixed vtk3DPanoramicReconstructor together with Noby | x | Fri Dec, 5th | ||
NDI Tracker module works | x | Wed Dec, 3rd | ||
December | Week 49 | 01.12 - 07.12 | ||
- | ||||
Week 48 | 24.11 - 30.11 | |||
vtkVideoSource works | x | Mon Nov, 24th | ||
Week 47 | 17.11 - 23.11 | |||
3D Volume generated with mock-up images and mock-up tracking data | x | Mon Nov, 17th | ||
Week 46 | 10.11 - 16.11 | |||
Tracker Simulator works | x | Thu Nov, 13th | ||
Week 45 | 03.11 - 09.11 | |||
Ultrasound Simulator works | x | Tue Nov, 4th | ||
November | Week 44 | 27.10 - 02.11 | ||
Starting work on "Creating a 3D-Volume with Synchrograb" | ||||
Week 43 | 20.10 - 26.10 | |||
Send Volume Data via OpenIGTLink from SynchroGrab to Slicer | x | Tue Oct, 14th | ||
Compile SynchroGrab (using latest OpenIGTLink Library) | x | Tue Oct, 14th | ||
Week 42 | 13.10 - 19.10 | |||
Understand and Use OpenIGTLink | x | Tue Oct, 7th | ||
Week 41 | 06.10 - 12.10 | |||
Get CUDA Rendering Volume working in Slicer | x | Wed Oct, 2nd | ||
Set up CUDA driver on th303_d4_6 | x | Tue Sep, 30th | ||
October | Week 40 | 29.09 - 5.10 | ||
Set up Fedora 8 on th303_d4_6 | x | Fri Sep, 26th | ||
Totally Understand GradientDiffusion Filter Module | x | Thu Sep, 25th | ||
September | Week 39 | 22.09 - 28.09 |