'''Agenda'''
 
'''Agenda'''
  
* Implementation of retrieve portion of mi2b2 - hardware solutions
+
* mi2b2 - hardware solutions (con't)
 
* Progress update
 
* Progress update
 +
* "Level of Service" discussion
  
 
== Harvard Catalyst Medical Informatics group Meeting Minutes April 13, 2010 ==
 
== Harvard Catalyst Medical Informatics group Meeting Minutes April 13, 2010 ==
Line 24: Line 25:
 
* Alex Zeitsev
 
* Alex Zeitsev
 
* Yong Gao
 
* Yong Gao
?
+
* Jesse Wei (phone)
* Jesse Wei
 
 
<br>
 
<br>
  
Line 45: Line 45:
 
Oracle 10g Express Edition (for Linux Servers) or Sql Server 2005 Express Edition (for Windows) <br>
 
Oracle 10g Express Edition (for Linux Servers) or Sql Server 2005 Express Edition (for Windows) <br>
 
Connected to the intranet with a fixed IP address, inside firewall with PACS access but no access to outside world.   
 
Connected to the intranet with a fixed IP address, inside firewall with PACS access but no access to outside world.   
# "Level of Service" statement for mi2b2.  All project personnel will need to be added to their site's i2b2 IRB development protocol to cover our work on this project.  Shawn is the PI for this IRB at MGH and BWH.  He will add Kathy, Mike, Darren, Tom, and Steve at MGH and BWH.  Shawn will send the text needed for this amendment to Griffin Webber who is PI at BIDMC to add Jesse.  Who at CHB is the analogous person? Idea of having key personnel (e.g. Chris Herrick) at MGH site from this project would apply for VPN privileges at BIDMC and CHB to that he would have access to all four sites to provide support. Host site can "turn it off" at any time if anything goes wrong.
+
# "Level of Service" statement for mi2b2.  We are now at a point where we need to secure appropriate IRB approval for all project personnel who access the medical imaging data for this effort.  Each site will identify who that is and they will need to take the CITI human subject's protection training course (https://www.citiprogram.org/) if not already done and then be added to their site's i2b2 IRB development protocol.  Shawn is the PI for this IRB at MGH and BWH.  He will add Kathy, Mike, Darren, Tom, (another name I missed) and Steve to his IRB that covers MGH and BWH.  Shawn will send the text needed for this amendment to Griffin Webber who is PI at BIDMC to add Jesse.  Shawn will find out who at CHB is the analogous person to add Paul and Bill. In addition, all key personnel (e.g. Chris Herrick at MGH site) who are going to provide service to the systems across sites for this project would need to be added to their respective IRBs prior to applying for VPN privileges at BIDMC and CHB to have access to all four sites to provide support.   Host site can "turn it off" at any time if anything goes wrong. But who is responsible to "turn it back on"? 
 
# Chris Herrick reported on his team's progress over the past week.  The i2b2 Star-D software is up and running in test mode.  Now working on "packaging" it so it is easy to deploy at all sites.  Will contain a miniature i2b2 version with only those components that are needed for this project.  <br>
 
# Chris Herrick reported on his team's progress over the past week.  The i2b2 Star-D software is up and running in test mode.  Now working on "packaging" it so it is easy to deploy at all sites.  Will contain a miniature i2b2 version with only those components that are needed for this project.  <br>
# Update from each site as to what configuration and how long before server will be in place.  (CHB) Paul and Bill have a laptop computer already.  (BIDMC) Jesse is applying for sign off from Radiology for project as a whole.  Hardware solution will await this team's input.  (BWH) Kathy is going to order a brand new WindowsXP desktop that she will order immediately and deploy it at the Kent Street facility computer room at the Center for Evidence Based Imaging (CEBI). (MGH) Darren discussed with his team and decided to go with a new laptop to be located on his desk, but will likely be WindowsXP. He also has to apply for sign off from Radiology for project as a whole.   
+
# Update from each site as to what configuration and how long before server will be in place.  (CHB) Paul and Bill have a laptop computer already identified that will be uesed.  (BIDMC) Jesse is applying for sign off from Radiology for project as a whole.  Hardware solution will await this team's input.  (BWH) Kathy is going to immediately order a brand new WindowsXP desktop to deploy at the Kent Street facility computer room at the Center for Evidence Based Imaging (CEBI). (MGH) Darren discussed with his team and decided to go with a new laptop to be located on his desk, that will likely be WindowsXP. He also has to apply for sign off from Radiology for project as a whole.   
# Security Policy.  And that we ensure that are fully compliant with it. (encrypt development server laptops?; what ports are used; )
+
# ARRA progress reports were just due.  Randy to improve our coordination of this effort. Huge thanks to Jesse for his nice write up for BIDMC.   
# ARRA progress reports were just due.
 
# (include who pays what costs?)(what we offer to users)(what we offer to Department hosts, what we expect from them) May need to be staged.  Now in development phase, business hours with 2 day turnaround is fine, when it is enterprise, that is not likely.  We need power. Replacements within 2 days.  Who to contact if there is a problemProtocols for problems, (FAQ page).
 
  
 
'''Action Items'''
 
'''Action Items'''
  
# Randy, Chris & Shawn to outline draft Security Policy to review for next meeting
+
# Randy, Chris & Shawn to outline draft Security Policy to review for next meeting (still in progress)
# Use next meeting to outline Level of Service document together
+
# Use next meetings to continue to outline Level of Service document together
 +
# Circulate info for CITI training

Revision as of 15:48, 13 April 2010

Home < CTSC:ARRA.041310

Back to CTSC:ARRA supplement

Agenda

  • mi2b2 - hardware solutions (con't)
  • Progress update
  • "Level of Service" discussion

Harvard Catalyst Medical Informatics group Meeting Minutes April 13, 2010

In attendance:

  • Shawn Murphy
  • Kathy Andriole (phone)
  • Mike Clyne (phone)
  • Wendy Plesniak
  • Randy Gollub
  • Chris Herrick
  • Bill Telier
  • Steve Pieper
  • Dan Marcus (phone)
  • Paul Lamonica
  • Mark Anderson
  • Darren Sack
  • Alex Zeitsev
  • Yong Gao
  • Jesse Wei (phone)


Meeting Minutes
Chris reviewed the minimum specs for a server to host the i2b2 STAR-D software that would communicate with the local PACS.

2 GHZ processor
2 GB RAM
40 GB free space

Software (when we deploy):

Windows XP SP1 or CentOS (other Linux version possible)
JDK 6.0
JBoss 4.2.2
Apache Ant 1.6.5
Apache Axis2 1.1
Oracle 10g Express Edition (for Linux Servers) or Sql Server 2005 Express Edition (for Windows)
Connected to the intranet with a fixed IP address, inside firewall with PACS access but no access to outside world.

  1. "Level of Service" statement for mi2b2. We are now at a point where we need to secure appropriate IRB approval for all project personnel who access the medical imaging data for this effort. Each site will identify who that is and they will need to take the CITI human subject's protection training course (https://www.citiprogram.org/) if not already done and then be added to their site's i2b2 IRB development protocol. Shawn is the PI for this IRB at MGH and BWH. He will add Kathy, Mike, Darren, Tom, (another name I missed) and Steve to his IRB that covers MGH and BWH. Shawn will send the text needed for this amendment to Griffin Webber who is PI at BIDMC to add Jesse. Shawn will find out who at CHB is the analogous person to add Paul and Bill. In addition, all key personnel (e.g. Chris Herrick at MGH site) who are going to provide service to the systems across sites for this project would need to be added to their respective IRBs prior to applying for VPN privileges at BIDMC and CHB to have access to all four sites to provide support. Host site can "turn it off" at any time if anything goes wrong. But who is responsible to "turn it back on"?
  2. Chris Herrick reported on his team's progress over the past week. The i2b2 Star-D software is up and running in test mode. Now working on "packaging" it so it is easy to deploy at all sites. Will contain a miniature i2b2 version with only those components that are needed for this project.
  3. Update from each site as to what configuration and how long before server will be in place. (CHB) Paul and Bill have a laptop computer already identified that will be uesed. (BIDMC) Jesse is applying for sign off from Radiology for project as a whole. Hardware solution will await this team's input. (BWH) Kathy is going to immediately order a brand new WindowsXP desktop to deploy at the Kent Street facility computer room at the Center for Evidence Based Imaging (CEBI). (MGH) Darren discussed with his team and decided to go with a new laptop to be located on his desk, that will likely be WindowsXP. He also has to apply for sign off from Radiology for project as a whole.
  4. ARRA progress reports were just due. Randy to improve our coordination of this effort. Huge thanks to Jesse for his nice write up for BIDMC.

Action Items

  1. Randy, Chris & Shawn to outline draft Security Policy to review for next meeting (still in progress)
  2. Use next meetings to continue to outline Level of Service document together
  3. Circulate info for CITI training